Stack Work Advances While Answers Do Not
On June 17 and 18, HPD told the first meeting of the Roosevelt Island Steam Plant Demolition Community Advisory Group that smokestack demolition had no projected start date. Residents and the CAG would receive at least five business days’ advance notice once a date was set. Scaffolding around the stacks could not proceed until soil removal and backfill were complete and the area stabilized.