Three new tidal energy turbines entered the East River near Roosevelt Island on Thursday evening. The RITE project’s giant step forward.
By David Stone
The Roosevelt Island Tidal Energy Project (RITE), a potential game changer, made a splash this week. Around 9:00 P.M. on Thursday, Verdant Power lowered three new fifth generation turbines into the East River.

As reported earlier, this next phase of the RITE project joins turbines deployed in 2011, but are a significant step ahead. While larger and capable of generating more power, the new tidal energy turbines innovate in other ways.
Verdant says its “…novel TriFrame™ mounting system… is the next step on a pathway to global commercialization and profitable commercial operations.”
We caught up with CEO John Banigan and asked him for a brief overview.
The original set of turbines supplied energy to the old Gristedes, now Foodtown, and to Motorgate. The idea was a trial because nobody knew for sure if the equipment could survive powerful East River tides.
“We also are proud to be a New York-based company…” John Banigan
The fifth-generation turbines muscle up and will tie directly into ConEd’s Roosevelt Island power grid.

“This pre-commercial demonstration of the proprietary integrated system is designed to optimize the economics of installation and maintenance over the system’s 20-year life, and to prove performance,” Verdant explains.
“This design provides for readily scalable systems to larger sizes for deeper and faster tidal straits.”
RITE is the first tidal power project licensed in the United States, and Verdant eyes taking its lessons across the globe. Its TriFrame™ mounting system is unlike anything else in the world.
Contrast: New Tidal Energy Turbines… and the past…

When I talked with Verdant president Trey Taylor, the contrast was striking because Ravenswood set the backdrop.
“That provides twenty-four percent of New York City’s power,” he said, and it’s a fact little known to Roosevelt Islanders.
But Ravenswood is also New York State’s most polluting, still burning low grade #6 fuel oil. Don’t be fooled by “oil,” because as a former stationery engineer, I can tell you, it’s closer to tar.
New ideas and a promising future…
Taylor is an idea man, and he’s full of them.
As we waited for the new tidal energy turbines entering the water, he talked concepts for Roosevelt Island.
“I talked with RIOC,” he said, and just before the three pieces of groundbreaking equipment broke the surface, he was ten years ahead.
Taylor envisions a future where water, wind and solar merge to make Roosevelt Island a model for the world.
Complimenting tidal energy turbines, he sees solar panels atop Motorgate, and he likes catching wind energy as it swirls past residential complexes.
Returning to the present though, the new tidal energy turbines, clawed feet securely in the riverbed, will spin out power for one year. And then, Verdant pulls them up for inspection.
Along with learning about their durability, Verdant will have statistics about how much power they pushed into the Roosevelt Island grid.
And for Contrast: Verdant Power’s original install in 2011
More from the roosevelt island daily news
- New York City Health & Hospital’s Community Mural Project Graces Coler“Healing in Community,” a part of NYC Health & Hospitals’s mural project, went live on December 1st at Roosevelt Islands’s Coler Rehabilitation Center. It’s one of nine additions to the wide-ranging effort this year. by
- The “Eviction Machine” Now Slams Into Roosevelt IslandAs a community, we always thought we were immune from these things, but the “eviction machine” described in a New York Times article, is building up momentum, attacking Roosevelt Island’s most vulnerable residents. by David
- Who Just Made the Big Fat Silence You Didn’t Hear?It was RIOC, and that big fat silence billowed out in every direction as it had for months. Starting with brutal accusations in a lawsuit condemning a wide swath of Roosevelt Islanders as racists, the
- FDNY Canceled a Dozen Inspections, Including at a Brooklyn Public School, to Fast Track City Hall VIPFire chiefs raised concerns about favoritism in the earliest months of the Adams administration, internal emails obtained by THE CITY show, as well-connected developers like The Related Companies lobbied to cut the fire inspection
- The Pentagon Just Can’t Pass An AuditConservative lawmakers calling for cuts should start with the agency that can’t account for $1.9 trillion — not the programs Americans rely on. By Lindsay Koshgarian | November 29, 2023 The Pentagon just failed its audit —
One thought on “3 New Turbines Upgrade Roosevelt Island Tidal Energy Project”